Estimated timescales for new build

On 17 November 2015, the Cabinet approved the appointment of Kier Living Limited to develop phases 2 and 3 of the estate in a phased manner; the last phase to be developed being subject to the Compulsory Purchase Order being secured. 

Kier started work on site on 13 July 2017, with the exception of the phase that is subject to the compulsory purchase order. Vacant possession of the land is required by December 2017 to complete the development of all phases to within this contract with Kier by June 2018.

To complete the development of the estate, a final phase of new build homes is to commence in 2018. 